FAQs

I want to know more about…

I want to know more about…

Below is a list of frequently asked questions (FAQs) that you might have around specific topic areas related to the Route 28 Bypass Project. These questions are updated frequently and are based on your direct feedback. If you don’t see an answer to a question you have, no problem! Email us and we’ll work to make sure your voice is heard and your questions are answered.

FAQs

Select the topic of your choice and jump right
into the questions you care about most.

Select the topic of your choice and jump right into the questions you care about most.

My Home & Family

Housing & Residential Concerns

PWC DOT has begun the approximately 2-year Design and Engineering phase of the Route 28 Bypass Project, which will determine the exact location of the roadway. The PWC DOT will not know exactly which properties & residences will be impacted by the Bypass until the Design and Engineering phase is complete.

At the conclusion of the Design and Engineering phase, an official notification will be sent directly to impacted properties and residents. Residents who will be required to relocate will be entitled to Relocation Assistance and support from Prince William County. Negotiations that adhere to the Uniform Act, Section 4.2.3. of VDOTs Right of Way Manual of Instructions, are expected to occur throughout 2023.

Additional studies determining noise impacts will be conducted throughout the process. As studies are completed, they will be shared on the project website. The engineering firm will work to identify appropriate solutions, such as noise barriers, for the Bypass.

While the noise analyses are not required as part of the project, PWC DOT will complete them to address concerns raised by the community

The Route 28 Bypass project is expected to cost approximately $300 million.

  • The NVTA has allocated $6 million to conduct numerous studies & reports in the beginning of the Planning Phase of the project and $89 million in regional funds to design and construct the bypass.
  • Prince William County residents voted on and approved a Mobility Bond Referendum in November of 2019 (with a 73% approval rating) which will provide $200 million of funding to the project if authorized by the Board of County Supervisors.

Based on the Virginia Code and the Uniform Act, Section 4.2.3 of VDOTs Right of Way Manual of Instructions, PWC officials will begin the process of meeting with property owners once the Board of County Supervisors has approved the final bypass design and the Right of Way impacts have been identified. The PWC DOT will notify and work with impacted property owners and residents throughout this process.

As the project continues, PWC DOT will regularly communicate and engage with the PWC community to make resources & information regarding the Route 28 Bypass easily accessible and understandable.

Information regarding the Right of Way process will also be posted on the Route 28 Bypass project website and provided during public Information Sessions.

My Community

The Request for Proposal (RFP) for the design phase has been released, and is available on the Prince William County Procurement site.

We plan to select an Engineering Firm in early-2021.

The Request for Proposal will describe and clarify the criteria for selection.

As with any construction project, many factors can impact the timeline. As of Fall 2020, we anticipate that the Construction Phase will begin in 2025. The PWC DOT will update the project timeline as the design and engineering phase progresses.

 

The Prince William Board of County Supervisors is required to review and approve the final engineering design for the Route 28 Bypass as part of a Public Hearing.

PWC DOT will submit permits for the Route 28 Bypass to the US Army Corps of Engineers and several other agencies once substantial design is completed. It is expected that results regarding the permits will be released in late-2022/early-2023. This  joint permit application is required to determine impacts to wetlands within the project area, and will be evaluated by a number of agencies.

If the Army Corps of Engineers does not release the permit, the construction of the project along the current location cannot occur and will have to be reevaluated.

Yes, VDOT will have to approve certain design elements and permits as part of the project. VDOT will also be involved in the final design of the project. Once the project is completed, maintenance and ownership of the roadway will be handed over to VDOT.

Additional studies will be completed once an engineering firm is selected, as part of the Design and Engineering phase of this project. The analysis and findings from those studies will impact decisions made about the Route 28 bypass design. The findings will be published on route28bypass.com and shared in public meetings.

We are looking at FEMA guidelines and will consider all options to reduce the impacts of flooding as the Route 28 Bypass design moves forward which may include: relocating residents out of the flood zones and performing stream restoration to increase capacity. The PWC DOT will also be complete additional flood analysis by installing flood gauges in the area to address community concerns.

Yes, the Route 28 Bypass will include a shared use path along the length of the new roadway. The project provides the opportunity to connect Ben Lomond Park to 234 and beyond to eventually connect with the Broad Run trail corridor at Innovation Park.

My Environment

We are looking at FEMA guidelines and will consider all options to reduce the impacts of flooding as the Route 28 Bypass design moves forward which may include: relocating residents out of the flood zones and performing stream restoration to increase capacity.

PWC DOT will submit permits for the Route 28 Bypass to the US Army Corps of Engineers once substantial design is completed. It is expected that results regarding the permits will be released in late-2022/early-2023. This permit is required to determine impacts to wetlands within the project area.

If the Army Corps of Engineers does not release the permit, the construction of the project along the current location cannot occur and will have to be reevaluated.

Additional studies will be completed once an engineering firm is selected, as part of the Design and Engineering phase of this project. The analysis and findings from those studies will impact decisions made about the Route 28 bypass design. The findings will be published on route28bypass.com and shared in public meetings.

My Commute

Regional Tie-In & Connections

The current concepts indicate that the Route 28 Bypass will connect to Route 28 utilizing part of Ordway Road and turning east to connect to existing Route 28 south of Compton Road and north of Bull Run.

However, until the Design and Engineering Phase is complete, we will not know the definitive location of the bypass.

PWC DOT will be consulting Fairfax County residents throughout the Design and Engineering Phase of the project and will provide property owners the opportunity to share input throughout the project. Prince William County in coordination with Fairfax County will host numerous information meetings to ensure that residents are aware of the latest developments. Materials from the most recent community information session can be found on the project website under Project Resources.

The Fairfax County Board of Supervisors has not taken any action regarding this project. The current plans largely anticipate improvements in Fairfax County to remain primarily along the Ordway Road Corridor. Based on these plans, the northern portion of Ordway Road would remain a two-lane roadway. The project corridor and potential impacts identified on the southern portion of Ordway Road will be refined throughout the design process and will likely be significantly reduced.

The City of Manassas currently has an active project installing turn lanes at the intersection at Sudley Road and Godwin Drive, which will be finished by the time construction of the Bypass begins.

Skip to content